No blanket extension of ALMM List-II for solar PV cells beyond 1 June 2026; case-to-case relief allowed
Practice PYQs on this topic
500+ questions on Environment with explanations
๐ Summary:
- The Ministry of New and Renewable Energy (MNRE) decided there will be no blanket extension of the deadline for applicability of the Approved List of Models and Manufacturers (ALMM) List-II for solar PV cells beyond 1 June 2026
- Under the existing framework, Net-Metering and Open Access projects commissioned before 1 June 2026 are exempt from ALMM List-II; projects commissioned after that date must comply
- The decision followed representations from stakeholders โ some sought an extension while others opposed it
- MNRE considered a Department of Expenditure memorandum (29 April 2026) which advised treating the ongoing West Asia situation as war and suggested a time extension of 2-4 months on a case-specific basis, not a blanket one
- To protect investments already made, certain Net-Metering, Open Access and Renewable Energy projects will be granted case-to-case time extensions โ where modules are installed but commissioning is pending, or where effective steps (land acquisition, financial closure, connectivity, approval of electrical drawings) have been undertaken
- Developers may submit claims with documentary proof through a dedicated portal of the National Institute of Solar Energy (NISE) by 30 June 2026; an Expert Committee will examine them
- Residential consumers under the "Give It Up" campaign of PM Surya Ghar: Muft Bijli Yojana remain governed by existing guidelines until 31 March 2027
- Aim: ensure policy stability in the solar PV manufacturing ecosystem and make India self-sufficient in solar PV manufacturing
๐ฏ UPSC Relevance: GS3 (Environment) โ renewable energy, domestic solar PV manufacturing, energy security and Atmanirbhar Bharat in clean energy.
๐ Prelims Facts:
- ALMM = Approved List of Models and Manufacturers; List-II applies to solar PV cells
- ALMM List-II applicability deadline: 1 June 2026
- The claims portal is operated by the National Institute of Solar Energy (NISE)
- PM Surya Ghar: Muft Bijli Yojana is a rooftop solar scheme; its "Give It Up" campaign lets consumers voluntarily forego the subsidy
๐ Key Term: ALMM (Approved List of Models and Manufacturers) โ a list maintained by MNRE of eligible solar PV models and manufacturers (List-I covers solar modules, List-II covers solar PV cells), mandated for government-supported projects to promote domestic manufacturing.
ALMMsolar PVMNRERenewable EnergyNISE
UPSC Classification
Prelims (GS1)
PrelimsMains
See PYQs related to โEnvironmentโ
Every classification tag above links to actual UPSC questions asked on that topic โ with answer, explanation and elimination logic. Only in the app.